            Operation is finished before planned time, what do we do?

            If your production is getting completed before the planned time. You can do following things:

            1: First and most important, correct the capacity (cycle time) for the machine, product and operation in question so that this does not happen again. 
            2: You can update the production quantity of this task and submit
            3: Click on "Force Reschedule" to reschedule the plan. At this time, the system will find available machine and will then plan any other task on this machine as per the priority of the job cards you have assigned.